Half Yearly Report and Accounts
Released
Released
Announcement PDF
BUXTON RESOURCES LIMITED
ABN 86 125 049 550
INTERIM FINANCIAL REPORT
FOR THE HALF YEAR ENDED
31 DECEMBER 2015
This interim financial report does not include all the notes of the type normally included in an annual
financial report. This report is to be read in conjunction with the Annual Report for the year ended 30 June
2015 and any public announcements made by Buxton Resources Limited during the interim reporting
period in accordance with the continuous disclosure requirements of the Corporations Act 2001.
BUXTON RESOURCES LIMITED
Contents
Page
Corporate information
3
Directors’ report
4
Auditor’s independence declaration
17
Condensed statement of profit or loss and other comprehensive income
18
Condensed statement of financial position
19
Condensed statement of cash flows
20
Condensed statement of changes in equity
21
Notes to the condensed financial statements
22
Directors’ declaration
26
Independent review report to the members of Buxton Resources Limited
27
2
BUXTON RESOURCES LIMITED
CORPORATE INFORMATION
Buxton Resources Limited
ABN: 86 125 049 550
Directors
Seamus Cornelius
Eamon Hannon
Anthony Maslin
Liu Xing Zhou
Auditors
Rothsay Consulting Services Pty Ltd
Level 1, Lincoln Building
4 Ventnor Avenue
West Perth WA 6005
Company Secretary
Sam Wright
Registered office and principal place of business
Suite 1, 1st Floor
14-16 Rowland Street
Subiaco WA 6008
PO Box 9028
Subiaco WA 6008
Ph: 08 9380 6063
Fax: 08 9381 4056
Web: www.buxtonresources.com.au
Share Register
Computershare Ltd
Level 11, 172 St Georges Tce
Perth WA 6000
Home Exchange
ASX Limited
ASX Code: BUX
3
BUXTON RESOURCES LIMITED
DIRECTORS’ REPORT
Your directors are pleased to present their report on Buxton Resources Limited for the half-year ended 31
December 2015.
DIRECTORS
The names of the directors who held office during or since the end of the half-year are:
Seamus Cornelius
Anthony Maslin
Liu Xing Zhou
Eamon Hannon (appointed 25 February 2016)
Julian Stephens (resigned 12 August 2015)
Directors were in office for the entire period unless otherwise stated.
REVIEW AND RESULTS OF OPERATIONS
Operating results
The Company recorded a loss for the period ended 31 December 2015 of $2,204,956 (2014; $1,711,566).
At 31 December 2015 the Company held cash and term deposit balances of $2,057,201 (2014; $1,919,664).
Double Magic Ni & Cu – West Kimberley
During the half year, Buxton announced that final assay results were been received for both diamond core
holes sampled as part of Phase 2 drill program at the Double Magic Ni-Cu Project (location in Figure 9). Three
separate targets have now returned drillhole intercepts >3% Ni, with results of up to 8.14% Ni in diamond
drill core (see Table 1 & 2 below).
The Double Magic Project has been confirmed by drilling as hosting better than economic Ni-Cu grades and
thicknesses, marking a historic turning point for mineral exploration in the West Kimberley. Five months after
entering the region, Buxton has become the first explorer to detect high grade magmatic sulphides in the
Ruins Dolerite, confirming the genetic model, exploration vectors, and potential of the project area to host
significant nickel-copper deposits. This success is despite more than 50 years of exploration by other parties,
validating Buxton’s acquisition of the Double Magic project in late April 2015.
Importantly, all geophysical targets (conductors) drill tested to date have proven to be related to nickelcopper sulphide mineralisation, with no false conductors identified. This is of particular relevance given the
number of new VTEM conductors now identified further to the east (Fireant Prospect and elsewhere) where
no previous exploration has been undertaken.
Summarising achievements to date, Eamon Hannon, Buxton’s CEO said: “Buxton can certainly be pleased
with, and proud of, the significant advancements the small team has made at the Double Magic project in
the past 5 months. Over this short period of time, the company has proven for the first time the existence
of thick and high grade nickel and copper mineralisation within the Ruins Dolerite.”
“Buxton has the first mover advantage in what we now consider exceptionally prospective ground, in one of
the world’s best jurisdictions for exploration.”
“The company has immediate follow up drilling targets at Conductors B, C and D and in addition numerous
high priority new targets in previously unexplored areas.”
4
BUXTON RESOURCES LIMITED
“The Buxton team is greatly buoyed with these results and we are counting down the days until returning to
Double Magic for Phase 3 exploration targeting significant nickel-copper accumulations, once weather and
access permits.”
In-depth Review of Exploration Results
An in-depth review of results from the Merlin Prospect (area of exploration to date), incorporating structural
data from core, full 3D analysis of geology, and a review of geophysical data, has revealed multiple additional
drill targets at and around Conductors D and A-B.
Regionally, analysis of finalised VTEM results from the aerial survey flown in October (~55km2), combined
with data from the regional heli-mapping completed in August, has identified 8 high priority targets within
large volumes of completely un-explored Ruins Dolerite to the east (Fireant Prospect). The targets have
primarily been identified by strong VTEM conductors which appear much longer and/or larger in area than
any previously seen in the region. These outstanding targets will be followed up as soon as weather
conditions allow with more detailed geological mapping, rock chip sampling and ground geophysics, to
further refine drillhole targeting.
Assay Results
Final assays have been received for both the diamond core holes samples sampled, DMDD0003 at Conductor
C and DMDD0004 at Conductor D. Samples are of HQ3 quarter core, 1 metre in length or less as determined
by geological logging. Core from the holes drilled as twins of DMRC0003 and DMRC0017 (DMDD0001 and
DMDD0002) is being retained intact for ongoing technical studies so has not been sampled.
Assay results have confirmed previously-reported visual assessment of core. Several different styles and
types of mineralisation have been confirmed with varying levels and ratios of the main sulphides pyrrhotite,
pentlandite, and chalcopyprite. Grades of up to 8.14% Ni have been intersected in core. See Figures 1, 2 and
3 for a section and plan of Conductor D, and a plan of the central area of the Double Magic Project.
See Figures 4 and 5 for core photographs of high-grade mineralisation at Conductors D and C.
A full listing of all >0.25% and >1% Ni intercepts from the two diamond core holes is provided below in Table
1. All Buxton’s RC drilling results were previously reported on 2nd November 2015. A summary of high grade
>3% Ni intersections from all Buxton drilling (RC and diamond core) is provided below in Table 2. Full spatial
detail for all Buxton’s drillholes is provided in Table 3.
The company reminds readers that mineralised intercepts reported are not to be considered as true
thicknesses. At Conductor D, the interpreted general geometry of mineralisation indicates that true thickness
of the 17 metre high-grade intersection in discovery hole DMRC0003, is probably around 6-8 metres. True
thicknesses elsewhere at Merlin are likely to be between 40% and 100% of the drillhole intersection length.
Note that massive sulphide geometries in particular can be very irregular to amorphous, making true
thickness estimates difficult.
5
BUXTON RESOURCES LIMITED
Table 1: Significant (>0.25% Ni) intersections for all Buxton diamond core drillholes sampled. Intersects and
sub-intersects >1% Ni highlighted in bold font.
Table 2: >3% Ni intersections from all Buxton drilling at Double Magic. These are high-grade highlights from
RC drilling results previously reported, and high-grade highlights from the diamond core results reported in
Table 1 above.
6
BUXTON RESOURCES LIMITED
Interpretative Comments
An interpretation of mineralisation geometry and genesis at the Merlin Prospect (Double Magic Project) has
been developed incorporating all new data collected during the recently completed 2015 field season.
Nickel-copper sulphide mineralisation is interpreted to occur both as primary magmatic accumulations in the
original mafic-ultramafic melt, and as structurally remobilised and/or enriched veins or pods. Buxton is the
first explorer to detect high grade magmatic sulphides in the Ruins Dolerite of the West Kimberley, confirming
the genetic model, exploration vectors, and potential of the project to host significant deposits.
At Conductor D, the high grades, textural characteristics, overall geometry of mineralisation, lithogeochemistry, and juxtaposition of differing rock types suggest that mineralisation represents a primary
accumulation of sulphides proximal to a feeder conduit. The feeder conduit or related structural feature was
then subsequently stoped out by the later, barren, highly magnetic dolerite dyke identified during mapping
in August. Several such dykes have been mapped in the area, generally between 10 and 30 metres thick,
dipping approximately at right angles to the interpreted original Ruins Dolerite sill orientation.
Some limited remobilisation of sulphides has also occurred at Conductor D, possibly during later regional
tectonism.
Figure 1 – Schematic cross-section of Conductor D, showing selected drillholes, summarised Ni/Cu assay
results, interpreted geology, and interpreted mineralisation extents. Section line below in Figure 2.
7
BUXTON RESOURCES LIMITED
Figure 2 – Conductor D plan view, showing drill hole collars & traces with summarised Ni/Cu assay results,
and interpreted geology.
8
BUXTON RESOURCES LIMITED
Figure 3 – General plan view of the central area of the Merlin Prospect at the Double Magic Project, showing
conductors, drill hole collars, and interpreted geology.
Mineralisation seen at Conductors A, B, C, H and I (as well as at Jack’s Hill) exhibits much greater structural
influence, particularly where higher grades occur. However, the enveloping low-grade disseminated sulphide
zones may represent primary mineralisation, albeit much more distal from any feeder conduit than
Conductor D.
Figure 4 – Close up core photo of massive sulphide intercept in DMDD0003 at Conductor C. Interval (0.2m
downhole) assayed 6.35% Ni. Note core is HQ3, with a diameter of ~61.1mm.
Figure 5 – Close up core photo of irregular top contact of massive sulphide vein in DMDD0004 at Conductor
D. Interval (0.5m downhole) assayed 8.14% Ni. Note core is HQ3, with a diameter of ~61.1mm.
Detailed review of ground and aerial geophysical results in conjunction with geological and structural
interpretations indicate substantial un-tested potential exists at Conductors D, A-B, and possibly C. High
grade mineralisation at Conductor D itself remains open along strike in both directions to the north-west and
south-east, as well as down-plunge to the south-west.
The potential for additional separate, fault-dislocated high-grade pods, particularly to the west of Conductor
D and/or at depth, is also considered to be excellent. Fault displacements of between 20 to 200m are
documented at Panoramic Resources’ Sally Malay deposit in the East Kimberley (Savannah Operations),
considered the most relevant model for mineralisation at Double Magic and Merlin. These faults are often
low-angle (flat) and therefore difficult to detect with geophysical methods. Several un-explained diffuse
VTEM anomalies exist at interpreted structural intersections, these may indicate the presence of deeper,
fault-displaced conductors which have yet to be drill-tested.
9
BUXTON RESOURCES LIMITED
Geophysics
Processing and evaluation of geophysical data has been completed. These datasets include the down-hole
TEM logging of 15 selected drillholes, the high power large fixed loop TEM survey, and the regional heli-borne
VTEMmax survey over the balance of Buxton’s tenements, coverage as depicted in Figure 6 below.
Preliminary DHTEM and FLTEM results were fully utilized during the field season to target drill holes.
Finalisation of data processing, interpretation and full reporting of these surveys has now further assisted
Buxton during development of mineralization and exploration models for Double Magic.
The 2015 VTEM survey completed over previously un-explored ground yielded outstanding results.
Numerous long, large and strong VTEM anomalies occur at the Fireant Propsect within areas mapped as Ruins
Dolerite approximately 10-15km to the east of the Merlin Prospect which has been the focus of exploration
up until now.
Additionally, many smaller discrete VTEM anomalies have also been identified of similar or larger size to
those initially identifying Conductors A-B and D in 2013. From this total of 22 newly identified VTEM targets,
eight have been selected for immediate on-ground follow-up as soon as access is possible at the end of the
northern wet season. This ground follow-up will include more detailed geological mapping, rock-chip
sampling and ground geochemical traverses, as well as ground geophysics, to refine drill targets.
The 2015 VTEM survey was flown on north-south, 100 metre spaced flight lines, identical with the 2013
survey specifications. Refer to Figures 6, 7 & 8 for survey coverage areas and locations of areas of interest.
Figure 6 – Map of Buxton’s Double Magic tenement package, showing tenements, prospect areas, survey
coverage from previous (2013) and new (2015) VTEM surveys and boxes showing the extent of Figures 7 and
8.
10
BUXTON RESOURCES LIMITED
Figure 7 – Map of Buxton’s 2015 field season area of focus at the Merlin Prospect, highlighting Conductors AD (all now known to be related to Ni-Cu mineralisation), over a merged image of the 2013 & 2015 VTEM
survey data (latest VTEM channel - CH48BZ).
Figure 8 – Map of Buxton’s new Fireant prospect, showing 8 new priority VTEM anomalies to be followed up
as soon as weather permits, over an image of the 2015 VTEM survey data (latest VTEM channel - CH48BZ).
11
BUXTON RESOURCES LIMITED
Table 3 – Buxton’s completed drilling at the Merlin Prospect, Double Magic Project. Coordinates are MGA
Zone 51 (GDA94)
12
BUXTON RESOURCES LIMITED
Figure 9 – Location of the Double Magic Ni-Cu Project in Western Australia. Also shown is the location of
Panoramic’s Savannah Ni-Cu Mine.
Zanthus Ni & Cu – Fraser Range
The Company’s 100% owned, highly prospective Zanthus Ni-Cu Project is located 60km along strike from
Sirius Resources’ Nova-Bollinger Ni-Cu discovery in the Fraser Range Nickel province, Western Australia.
The Company’s drilling program targeted two conductors, ZM02 and ZM07. Hole ZRC095 on conductor ZM02
was completed at 306m with a zone of disseminated pyrrhotite and minor chalcopyrite in gneiss over 20m
explaining the conductor. No significant Ni-Cu mineralization was encountered.
Zanthus hole ZRC096 targeting the large ZM07 conductor at ~700m depth has been temporarily suspended
at 256m due to technical difficulties associated with running sands in the top 40m of the hole. Additionally,
the drilling contractor has undertaken to re-mobilise to Zanthus and re-enter (or re-drill to the previously
reached depth) ZRC096 at no cost to Buxton.
Yalbra Graphite – Gascoyne Region
Buxton reported initial flotation and acid purification test-work results for its high-grade Yalbra Graphite
Project in Western Australia.
Flotation batch test results from a representative fresh rock diamond drill sample grading 20.0% C(t) returned
a concentrate grade of 91% C(t). This concentrate showed a good proportion of medium to coarse flake
material with 30% falling into categories above +149 microns in size (Table 1). The overall recovery of graphite
was 80%, although this should be improved in future locked cycle tests. The process involved a primary grind,
a rougher flotation stage, 2 stages of polishing grind and 5 cleaner flotation stages.
13
BUXTON RESOURCES LIMITED
A final leaching stage using a combined H2SO4/HF solution to upgrade the concentrate was also completed
and showed that a final concentrate grading 99.5% C(t) could be achieved, with the coarser size fractions
grading as high as 99.7% C(t).
Yalbra is Australia’s highest reported grade graphite resource at 4.0Mt @ 16.2% TGC (Inferred) and has
considerable potential to be expanded along strike, and for discovery of additional resources. Additionally,
Buxton has shown commercial products can be produced from its very high grade Yalbra Graphite Project.
As such, the Company is now in a position to seek a development and/or offtake partner to assist in
commercialising the project.
Table 1. Flotation and purification results for the Yalbra Graphite Project.
Size
Microns (µm)
Size
Tyler Mesh
Assays
Assays
Flotation Conc.
Purified Conc.
C (t) %
C (t) %
Distribution
C (t) %
+297 µm
+48 mesh
91.8
99.7
6.6
+149 µm
+100 mesh
90.6
99.7
22.8
+74 µm
+200 mesh
90.0
99.5
31.2
-74 µm
-200 mesh
91.7
99.1
39.5
90.9
99.5
100.0
Weighted Avg.
Competent Persons
The information in this report that relates to exploration results and geology for the Double Magic Project is based on information
previously reported under the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves based on information compiled by Mr Rolf Forster, Member of the Australasian Institute of Mining and Metallurgy, and Mr
Derek Marshall, Member of the Australian Institute of Geoscientists. Mr Forster is an Independent Consultant to Buxton Resources
Limited and Mr Marshall is a full-time employee. Mr Forster and Mr Marshall have sufficient experience which is relevant to the
activity being undertaken to qualify as a “Competent Person”, as defined in the 2012 edition of the Joint Ore Reserves Committee
(JORC) Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Forster and Mr Marshall
consent to the inclusion in this report of the matters based on the information in the form and context in which it appears.
The information in this report that relates to exploration results and geology for the Yalbra and Zanthus projects is based on
information previously reported under the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves based on information compiled and/or reviewed by Mr Eamon Hannon, Fellow of the Australian Institute
of Mining and Metallurgy and Managing Director at Buxton Resources Limited. No material changes have occurred to this information.
Mr Hannon has sufficient experience which is relevant to the activity being undertaken to qualify as a “Competent Person”, as defined
in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves and consents
to the inclusion in this report of the matters reviewed by him in the form and context in which they appear. There have been no
material changes to the information reported in the previous report.
The information in this report that relates to in-situ Mineral Resources is based on information compiled by David Williams of CSA
Global Pty Ltd and previously reported 25/2/2014. David Williams is a Member of the Australasian Institute of Mining and Metallurgy,
and a Member of the Australian Institute of Geoscientists and has sufficient experience, which is relevant to the style of mineralisation
and type of deposit under consideration, and to the activity he has undertaken, to qualify as a Competent Person in terms of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (JORC Code 2012 Edition). David
Williams previously consented to the inclusion of such information in the previous report in the form and context in which it appeared.
There have been no material changes to the information reported in the previous report.
14
BUXTON RESOURCES LIMITED
VTEM Survey Parameters
Helicopter-borne Time Domain Electromagnetic Survey
VTEM max system – UTS Geophysics Pty Ltd
Flight line specifications – Line Spacing 100m, Line Direction 0-180, Line Kilometres 557
Optimum terrain clearances – Helicopter 90m, EM sensor 35m, Magnetic sensor 75m
Airspeed/data collection – Normal airspeed approx. 90km/hr, data-recording rate 10 points per second, geophysical measurements
acquired approx. every 2m along survey lines
VTEM max Configuration – Transmitter loop diameter 36m, Peak dipole moment 865,000 NIA, Transmitter Pulse Width 5ms, VTEM
receiver Z,X coils
Real time GPS – Novatel WAAS OEM4-G2-3151W, position accuracy (CEP) is 1.8m, with WAAS on 1.2m
Altimeter system – ground clearance recorded to an accuracy of approx. 1m. Output repetition rate of 0.5sec.
CORPORATE
During the period the Completed raised $2,000,700 before issue costs through the issue of 10,260,000 shares
at an issue price of 19.5 cents. A further $25,000 was raised through the issue of 250,000 shares at an issue
price of 10 cents.
During the period the Company issued 7,350,000 unlisted options to Directors, employees and consultants.
The options have an exercise price of 12 cents and an expiry date on 30 November 2019.
ANNUAL GENERAL MEETING
Buxton held its Annual General Meeting of Shareholders on 30 November 2015 at Steve’s Wine Cellar, 30
The Avenue, Nedlands, Western Australia and all resolutions that were put were unanimously passed on a
show of hands.
SIGNIFICANT EVENTS SUBSEQUENT TO REPORTING DATE
On 25th February 2016, Buxton announced the appointment of Eamon Hannon as Managing Director.
Mr Hannon, a geologist and Fellow of the AusIMM, has a wealth of experience within the minerals industry
from grass roots exploration through to project development., Having previously worked for Fortescue
Metals Group (ASX: FMG) from early 2004 to late 2012 in the role of Director, Exploration and Evaluation, he
lead the teams to delineate in excess of 10 billion tons of iron ore resources and greater than 1 billion tons
of iron ore reserves.
Since his appointment as Buxton CEO in October 2014, Mr Hannon has overseen the acquisition of the 100%
interest in the Double Magic Nickel Project in the Kimberley region of Western Australia and has further
advanced the Company’s highly prospective nickel-copper projects in the Fraser Range, as well as the
Company’s very high grade Yalbra Graphite Project.
Buxton Resources Chairman, Seamus Cornelius, commented:
“We are delighted to have Mr Hannon join the Buxton Board. His experience and capabilities, both from an
exploration, mine development and corporate leadership standpoint, are an asset to Buxton.”
Subsequent to the balance date no matter or circumstance, other than the above, has arisen which has
significantly affected, or may significantly affect the operations of the Company, the result of those
operations, or the state of affairs of the Company in subsequent financial years.
15
BUXTON RESOURCES LIMITED
AUDITOR’S INDEPENDENCE DECLARATION
A copy of the auditor’s independence declaration as required under section 307C of the Corporations Act
2001 is set out on the following page.
This report is made in accordance with a resolution of directors.
Seamus Cornelius
Director
Perth, 15th March 2016
16
OTHSAY
Level 1, Lincoln House, 4 VentnorAvenue, West Perth WA 6005
P.O. Box 8716, Perth Business Centre WA 6849
Phone 9486 7 094 www.rothsayresources'com'au
Independent Review Report to the Members of Buxton Resources Ltd
The financial report and directors' responsibility
The interim financial report comprises ihe statement of financial position, statement of comprehensive income,
and the
statement of changes in equity, cashflow statement, accompanying notes to the financial statements,
2015.
3l
December
period
ended
the
Ltd
for
Resources
for
Buiton
directors' declaration
The Company's directors are responsible for the preparation and fair presentation of the financial report in
accordance with Australian Accounting Standard AASB 134 Interim Financial Reporting and the Corporations Act
200t.This includes responsibility for the maintenance ofadequate accounting records and internal controls that are
designed to prevent and- detect fiaud and error, and for the accounting policies and accounting estimates inherent in
the financial report.
Review approach
We conducied our review in accordance with Auditing Standard on Review Engagements ASRE 2410 Review of an
Interim Financial Report Performed by the Independent Auditor of the Entity, in order to state whether, on the basis
of the procedures deicribed, we have become aware of any matter that makes us believe that the interim financial
report is not in accordance with the Corporations Act 2001 including: giving a true and fair view of the ftnancial
position as at 3l December 2015 and the performance for the half year ended on that date; and complying with
Australian Accounting Standard AASB 734 Interim Financial Reporting and the Corporations Regulations 200I . As
auditor of Buxton Resources Ltd, ASRE 2410 requires that we comply with the ethical requirements relevant to the
audit ofthe annual financial report.
A review of an interim financial report consists of making enquiries, primarily of persons responsible for financial
and accounting matters, and applying analytical and other review procedures. A review is substantially less in scope
than an audit conducted in accordance with Australian Auditing Standards and consequently does not enable us to
obtain assurance that we would become aware of all significant matters that might be identified in an audit.
Accordingly we do not express an audit opinion.
Independence
In conducting our review we have complied with the independence requirements of lhe Cotporations Act 2001.
Conclusion
Based on our review, which is not an audit, we have not become aware of any matter that makes us believe that the
interim financial report of Buxton Resources Ltd is not in accordance with the Corporations Act 2001 , including:
r
giving a true and fair view of the financial position of the company as at 3l December 2015 and of its
performance for the period ended on that date; and
.
complyrng with Australian Accounting Standard AASBI34 Interim Financial Reporting and the
Corporati ons Regulations 200 I .
A"rk*z
Rothsay Auditing
&s_
Graham R Swan
Dated t
Partner
5
March 2016
@
Chartered Accountants
Liability Limited by rhe Accountants Scheme, approved under the Professional Standards Act 1994 (NSW).
BUXTON RESOURCES LIMITED
CONDENSED STATEMENT OF PROFIT OR LOSS AND OTHER COMPREHENSIVE INCOME
FOR THE HALF-YEAR ENDED 31 DECEMBER 2015
Half-year ended
31 Dec 2015
$
31 Dec 2014
$
Revenue from continuing operations
7,845
5,534
Depreciation expense
(8,884)
(12,161)
Salaries and employee benefits expense
(275,105)
(377,948)
Share based payment expense
(324,883)
(465,395)
(1,432,311)
(657,942)
Corporate expense
(116,571)
(149,412)
Administration expense
(67,518)
(75,472)
(2,217,427)
(1,732,796)
12,471
21,230
-
-
12,471
21,230
(2,204,956)
(1,711,566)
-
-
(2,204,956)
(1,711,566)
(2.50)
(2.82)
Exploration and evaluation expense
Loss from operating activities
Finance income
Finance cost
Net finance income
Loss before income tax
Income tax expense
TOTAL COMPREHENSIVE LOSS FOR THE PERIOD
Basic and diluted loss per share (cents)
The above condensed statement of profit or loss and other comprehensive income should be read in
conjunction with the accompanying notes.
18
BUXTON RESOURCES LIMITED
CONDENSED STATEMENT OF FINANCIAL POSITION
AS AT 31 DECEMBER 2015
31 December
30 June
2015
$
2015
$
Cash and cash equivalents
2,057,201
1,954,686
Trade and other receivables
56,387
111,309
Other current assets
21,573
141,352
2,135,161
2,207,347
Deferred exploration expenditure
486,046
427,210
Plant and equipment
49,142
58,025
TOTAL NON-CURRENT ASSSETS
535,188
485,235
2,670,349
2,692,582
Trade and other payables
83,043
177,691
TOTAL CURRENT LIABILITIES
83,043
177,691
TOTAL LIABILITIES
83,043
177,691
2,587,306
2,514,891
Note
CURRENT ASSETS
TOTAL CURRENT ASSETS
NON-CURRENT ASSETS
TOTAL ASSETS
CURRENT LIABILITIES
NET ASSETS
EQUITY
Issued capital
3
14,884,485
12,931,994
Reserve
5
1,800,837
1,475,954
(14,098,013)
(11,893,057)
2,587,309
2,514,891
Accumulated losses
TOTAL EQUITY
The above condensed statement of financial position should be read in conjunction with the
accompanying notes.
19
BUXTON RESOURCES LIMITED
CONDENSED STATEMENT OF CHANGES IN EQUITY
FOR THE HALF-YEAR ENDED 31 DECEMBER 2015
Balance at 1 July 2014
Option reserve
Issued capital
Accumulated
losses
$
$
$
Total
$
9,836,381
(9,367,384)
1,052,053
1,521,050
-
(1,711,566)
-
(1,711,566)
1,800,400
-
-
1,800,400
Shares issued on conversion of
options
56,000
-
-
56,000
Shares issued to corporate advisor
34,000
-
-
34,000
(106,424)
-
-
(106,424)
-
-
431,395
431,395
Balance at 31 December 2014
11,620,357
(11,078,950)
1,483,448
2,024,855
Balance at 1 July 2015
12,931,994
(11,893,057)
1,475,954
2,514,891
-
(2,204,956)
-
(2,204,956)
2,025,700
-
-
2,025,700
58,837
-
-
58,837
(132,046)
-
-
(132,046)
-
-
324,883
324,883
14,884,485
(14,098,013)
1,800,837
2,587,309
Total comprehensive income for the
period
Shares issued for cash
Share issue costs
Share option payments
Total comprehensive income for the
period
Shares issued for cash
Shares issued under exploration
agreements
Share issue costs
Share option payments
Balance at 31 December 2015
The above condensed statement of changes in equity should be read in conjunction with the
accompanying notes.
20
BUXTON RESOURCES LIMITED
CONDENSED STATEMENT OF CASH FLOWS
FOR THE HALF-YEAR ENDED 31 DECEMBER 2015
Half-year ended
31 Dec 2015
$
31 Dec 2014
$
7,845
3,114
Payments for
Share your feedback
Discover