ZANTHUS AND DOUBLE MAGIC DRILLING PROGRAMS UPDATE
Zanthus hole ZRC095 on conductor ZM02 completed at 306m with a zone
of disseminated pyrrhotite with minor chalcopyrite in gneiss over 20m
explaining the conductor. Samples have been dispatched to the laboratory
and assays will be reported when available
Zanthus hole ZRC096 targeting the large ZM07 conductor at ~700m depth
has been temporarily halted at 256m due to technical difficulties associated
with running sands in the top 40m of the hole
ZRC096 to be continued at a later date once appropriate steel casing is
manufactured to case the top 40m of the hole
Buxton would like to thank our drilling contractors WHB Drilling Pty Ltd for
supporting the company with their obligation to re-mobilise to ZRC096 and
recover the hole at no cost to Buxton.
Field and drill crews are currently demobilising from Zanthus and will
immediately relocate to Double Magic to begin the ~ 2,500m RC drill
program
Eight separate conductors to be tested at Double Magic, including
conductor D with a conductance of up to ~15,000 siemens and associated
outcropping magmatic Ni-Cu sulphides
We refer readers to Buxton’s home page www.buxtonresources.com.au for
further detail on Double Magic’s drill program.
Drilling expected to commence at Double Magic in under two weeks
Competent Person
The information in this report that relates to rock chip sampling results was previously reported on 13/07/2015 and is
based on information compiled by Dr Julian Stephens, Member of the Australian Institute of Geoscientists and NonExecutive Director for Buxton Resources Limited. Dr Stephens has sufficient experience which is relevant to the
activity being undertaken to qualify as a “Competent Person”, as defined in the 2012 edition of the Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves and consents to the inclusion in this report
of the information compiled by him in the form and context in which they appear. The rock-chip results have not
materially changed since first reported.
The information in this report that relates to all other exploration results is information previously reported by Victory
Mines Limited (ASX: VIC) under the 2004 edition of The Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves ("JORC Code") on 12/09/2012, 10/10/2012, 25/10/2012, 16/01/2013,
13/03/2013, 24/04/2013, 29/05/2013, 11/06/2013, 20/06/2013, 05/07/2013, 06/08/2013, 12/08/2013 and 13/09/2013.
There have been no material changes to the Exploration Results reported in the announcements of Victory Mines
Limited. Buxton has not yet been able to completely verify all of the historical Exploration Results. Buxton will report
further in relation to the project once sufficient work has been completed to report under the 2012 Edition of the JORC
Code.
PO Box 9028
Subiaco WA 6008
Suite 1, First Floor
14-16 Rowland Street
Subiaco WA 6008
Tel: 08-9380 6063
Fax: 08-9381 4056
www.buxtonresources.com.au
info@buxtonresources.com.au
Share your feedback
Discover