29 April 2024
QUARTERLY ACTIVITIES REPORT
for the period ending 31 March 2024
Graphite Bull Project (100% BUX)
•
•
•
Successful electrochemical results from anode testwork by ProGraphite
GmbH
Heritage Survey allows for substantive resource upgrade drilling program
Commenced production of a ~200 kg bulk concentrate sample for
qualification testwork with prospective customers
Copper Wolf Project; Arizona USA (100% BUX, IGO option to earn 70%)
•
•
•
•
Mapping, rock chip sampling and drone magnetics
Porphyry system extended and discovery of outcropping Cu-Mo
mineralisation on 100% BUX tenure adjacent to the IGO JV tenure at the
Wolverine, Sun Devil and Aztecs prospects
Expansion to 100% BUX tenure holdings
Drill permitting submitted at Wolverine
Dogleg Nickel Discovery – West Kimberley JV Project (16% BUX)
•
•
23WKDD004 returned 2.89 m (True Width 2.63 m) at 4.17% Ni, 0.83% Cu,
0.14% Co from 233.63 m
IGO planning a substantive drill program for the 2024 field season
Centurion Project (100% BUX)
•
Submission of heritage survey requests to secure access to site
Corporate
•
Cash balance (31 March 2024) of approximately $1.22 million
Buxton Resources Limited (ASX: BUX or “Buxton”) is pleased to release the Quarterly
activities report and Appendix 5B for the period ended 31 March 2024 (the Quarter).
Graphite Bull Project (BUX 100%)
The Graphite Bull Project (Exploration License E09/1985) is located 280 km East of
Carnarvon in the Murchison Region of Western Australia. In 2014, Buxton released
an updated, JORC 2012 compliant, Mineral Resource Estimate for the main zone of
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
graphite mineralisation. The Inferred Mineral Resource is 4.0Mt @ 16.2% TGC, using
a 4% TGC cut-off (see ASX announcement 24th October 2014).
During the Quarter, continued the dual-stream electrochemical testwork aimed at
evaluating multiple process options for the Graphite Bull concentrate material.
Initial results from ProGraphite on the first bulk concentrate sample directed toward
the assessment of Li-ion battery quality benchmarks showed these were exceeded
by simple caustic bake purification achieving 99.97% TGC. Spheronising gave
excellent shape and size distribution, yield also above average. Concentrate
micronised well with relatively little energy input (see ASX Announcement 7th August
2023 for further details).
During the Quarter Buxton announced successful final results from electrochemical
& anode testing by ProGraphite GmbH in Germany (see ASX Announcement 25th
January 2024). The successful electrochemical work clearly demonstrates the
suitability of Graphite Bull feed for Li-ion Battery Anode manufacture and that
Graphite Bull uncoated Purified Spherical Graphite (uPSG) performed better in
anode testing than uPSG from other projects. This critical milestone, reached after
just 14 months of work in WA and Germany is a very positive result and has facilitated
strong interest in the project from several potential development partners.
During the Quater, Buxton also commenced the preparation of a ~200 kg bulk
concentrate sample at ALS Metallurgy. This material will be made available for
customer qualification testwork work. Buxton also undertook a heritage survey to
enable a significant resource extension and infill drilling program later in 2024 (see
ASX Announcement 19th March 2024).
Copper Wolf Project (BUX 100% / IGO option to earn 70%)
Buxton’s Copper Wolf Project consists of Lode Mining Claims and Mineral
Exploration Permits in Yavapai County, Arizona. The Copper Wolf Project has
multiple historical resource estimates available that confirm the presence of a large
Laramide porphyry Cu-Mo system (see ASX Announcement 25 October 2021).
Porphyry Cu-Mo mineralisation at Copper Wolf is largely concealed by a post-mineral
(Tertiary) sequence of volcanic and sedimentary rocks. The Project is located within
one of the most prolifically endowed copper belts in the world, yet it has not seen
any drilling since the early 1990s. Buxton’s 2022 airborne magnetic survey was the
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
first geophysical work undertaken since the early 1960s. Historic exploration has
consisted of relatively wide spaced drilling which focussed on significant supergene
copper mineralisation. Buxton is targeting high grade, underground bulk mineable
copper-molybdenum mineralisation.
On the 4th October August 2022, Buxton received shareholder approval for Buxton
and IGO to enter into an earn-in and joint venture agreement for the Copper Wolf
Project (Arizona, USA).
During the Quarter Buxton undertook mapping, rock chip sampling and drone
magnetic surveys at the Wolverine, Sun Devil and Aztecs prospects – see ASX
Announcements:
-
11th Jan 2024: Extension to Cu-Mo Porphyry System Discovered at Surface on
100% BUX Tenure at Wolverine Prospect
24th Jan 2024: Intense Porphyry Style Veining at Sun Devil on 100% BUX
Ground, Tenure Expansion & Wolverine Drill Permitting
13th Feb 2024: Porphyry drill targets identified at Sun Devil and Aztecs
prospects (BUX 100%)
11 Mar 2024: Highly Anomalous Rock Chip Assays at Sun Devil and Aztecs,
Drone Magnetics Commenced at Wolverine
Buxton also applied for a permit to drill at the Wolverine prospect.
Narryer Project (BUX 100%)
The Narryer Project is targeting magmatic Ni-Cu-PGE sulphide mineralisation along
the Yilgarn Craton margin within the Murchison Region of WA. The Narryer Project
consists of four ELs covering > 1800 km2. Buxton has completed substantive
systematic exploration programs since 2021, including regional gravity / airborne EM
programs and a ground EM program in early 2023 which defined high conductance
drill target at the Ranger Prospects, and a lower conductance target at the Bandito
prospect.
During the Quarter Buxton received results from the soil sampling program
undertaken in late 2023. Anomalous soil geochemistry was detected coincident with
a gravity high and along strike from existing ground EM conductor at Ranger.
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
A MLEM program is now planned to commence in Q2. This will extend ground EM
coverage at Ranger over the coincident gravity / soil anomaly. Buxton has also
scheduled Heritage Surveys to allow for drill testing the existing ground EM
conductor at the Ranger prospect.
West Kimberley Project (BUX / IGO JV)
The West Kimberley Project is targeting Nova-style magmatic Ni-Cu sulphide
mineralisation in Proterozoic belts of the West Kimberley Region of Western
Australia. Buxton have Farm-In and JV agreements over three separate Project areas
(Merlin Project, Quickshears Project and West Kimberley Regional Project) which fall
within the overall West Kimberly Project.
During the previous Quarter, IGO intersected massive sulphides in the maiden
drillhole at the Dogleg prospect. A second hole intersected semi-massive sulphides.
Assays received for the first Dogleg hole contained 13.85m (true width 13.24m) at
4.35% Ni, 0.34% Cu, 0.15% Co from 177.34m, including: 5.86m (true width 5.60m)
at 7.47% Ni, 0.31% Cu, 0.25% Co from 179.08m.
During the Quarter, Buxton announced assay results for the second hole
23WKDD004 returned 2.89 m (True Width 2.63 m) at 4.17% Ni, 0.83% Cu, 0.14% Co
from 233.63 m (see ASX Announcement 1st Feb 2024). These extremely high tenor
results lie outside the initial ground moving loop EM plate / drill target. JV partner
IGO Ltd has indicated that they intend to undertake a significant drilling program in
the 2024 field season (Q3-Q4) at Dogleg to follow-up this outstanding nickel sulphide
discovery.
Fraser Range Project (BUX 10% / IGO 90%)
Exploration The Fraser Range Project is targeting magmatic Ni-Cu sulphide
mineralisation along strike from IGO’s operating Nova mining operation. Buxton
remain free carried until completion of a feasibility study with Buxton retaining an
exclusive right to explore and develop iron ore on the Tenements. During the
Quarter, IGO reported having undertaken rehabilitation and targeting activities.
Centurion Project (BUX 100%)
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
The Centurion Project consists of Exploration License E80/5579 located
approximately 180 km south-southwest of Balgo Western Australia on unclaimed
crown land and accessible via shire roads and several 1960s-1980s seismic lines. This
license covers a prominent dipolar and offset magnetic and gravity gradiometer
anomalies characteristic of Iron Oxide Copper Gold deposits including Olympic Dam
and Prominent Hill. Magnetic data indicate that the target is located approximately
700 metres beneath ground level under post mineral cover sequences of the Canning
Basin.
During the Quarter, Buxton submitted heritage work programs to enable the reestablishment access along a historic seismic line.
Shogun & Royale Projects (BUX 100%)
The Shogun and Royale Projects form a contiguous package covering 2617 km2
located in the Paterson Region of Western Australia. Exploration on the two (2)
Shogun Project ELA 45/6533 and 45/6534 is targeting magmatic Ni-Cu-Co-PGE
sulphide deposits. The five (5) Royale Project ELAs (E45/6228 through E45/6232)
cover exploration targets for hydrothermal Cu +/- Au – Mo deposits.
During the Quarter, Buxton continued to undertake negotiations with the Native
Title group with a view to executing a Heritage Agreement.
Lateron Project (BUX 100%)
The Lateron Project consists of Exploration License E80/5545 located on unclaimed
crown land close to the Tanami Road, approximately 10 km East of Billiluna and 150
km South of Halls Creek in Western Australia. During the Quarter Buxton received
the results of petrological analysis on fragments of diamond drill core recovered from
the site of AFMECO’s 1982 diamond drillhole S19. The report indicates the core
fragments consist of “biotite hornblende quartz diorite, with coarse titanite and
sericite / muscovite pyrite-magnetite-chalcopyrite overprint” – such rocks are
typically associated with magmatic-hydrothermal Cu-Au mineralisation. Airborne
mag indicates these intrusive rocks cover > 7 km2.
During the Quarter Buxton continued negotiations with the new Native Title
Representative Body for the Tjurabalan People with a view to executing a Heritage
Agreement.
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
Project Generation
Buxton has continued to undertake generative work, both in Western Australia and
Arizona. Subsequent to the Quarter end, tenement E69/4182, “Madman Project”.
Was granted. Buxton will provide further details on this new 100% owned project in
the coming Quarter. Buxton also undertook detailed assessment of manganese and
copper opportunities in Arizona.
Corporate
The Company’s Quarterly Cashflow Report (Appendix 5B) follows this activities
report. The Company had $1.217 million in cash as 31 March 2024. Exploration
Expenditure for the Quarter was $0.494 million with most of this expenditure being
associated with field work in support of the Copper Wolf Project, metallurgical
studies in support of the Graphite Bull Project, along with other ongoing project
assessment. Buxton is also continuing to actively pursue copper and other
commodity opportunities in the USA.
The aggregate amount of payments to related parties and their associates included
in the current Quarter cash flows from operating activities were approximately $43k
comprising directors fees, salaries and superannuation. Corporate and other
administration expenditure was $132k for the Quarter which represents general costs
associated with running the Company, including ASX fees, legal fees, rent,
marketing, etc. Cash outflows for the Quarter were in line with management
expectations. The company is adequately funded to continue its current activities
and will continue to demonstrate appropriate fiscal management.
This announcement is authorised by the Board.
For further information, please contact:
Martin Moloney
Chief Executive Officer
marty@buxtonresources.com.au
Sam Wright
Company Secretary
sam@buxtonresources.com.au
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
Appendix 1
Changes in interests in mining tenements Buxton Resources Ltd
01/01/24 – 31/03/24
Tenement
% at
beginning
of Quarter
Location / Project
% at end of
Quarter
Interests in mining
tenements relinquished,
reduced or lapsed
Interest in mining
tenements acquired or
increased
* changes occurred between end of the Quarter and issuing this report
E04/2451
West Kimberley - Baracus / IGO JV
16
West Kimberley Regional - IGO JV
20
20
E04/2407
West Kimberley Regional - IGO JV
20
20
E04/2408
West Kimberley Regional - IGO JV
20
20
E04/2411
West Kimberley Regional - IGO JV
20
20
E04/2527
West Kimberley Regional - IGO JV
20
20
E04/2530
West Kimberley Regional - IGO JV
20
20
E04/2536
West Kimberley Regional - IGO JV
20
20
E04/2549
West Kimberley Regional - IGO JV
20
20
E04/2550
West Kimberley Regional - IGO JV
20
20
E04/2578
West Kimberley Regional - IGO JV
20
20
E04/2579
West Kimberley Regional - IGO JV
20
20
E04/2580
West Kimberley Regional - IGO JV
20
20
E04/2581
West Kimberley Regional - IGO JV
20
20
E04/2584
West Kimberley Regional - IGO JV
20
20
E04/2585
West Kimberley Regional - IGO JV
20
20
E04/2609
West Kimberley Regional - IGO JV
20
20
E04/2611
West Kimberley Regional - IGO JV
20
20
E04/2612
West Kimberley Regional - IGO JV
20
20
E04/2613
West Kimberley Regional - IGO JV
20
20
E04/2614
West Kimberley Regional - IGO JV
20
20
E04/2615
West Kimberley Regional - IGO JV
20
20
E04/2617
West Kimberley Regional - IGO JV
20
20
E04/2629
West Kimberley Regional - IGO JV
20
20
E04/2630
West Kimberley Regional - IGO JV
20
20
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
16
E04/2060
www.buxtonresources.com.au
E04/2631
West Kimberley Regional - IGO JV
20
20
E04/2648
West Kimberley Regional - IGO JV
20
20
E04/2649
West Kimberley Regional - IGO JV
20
20
E04/2650
West Kimberley Regional - IGO JV
20
20
E04/2651
West Kimberley Regional - IGO JV
20
20
E04/1972
West Kimberley – IGO/NWC/TT JV
16
16
E04/2314
West Kimberley – IGO/NWC/TT JV
16
16
E04/2423
West Kimberley – IGO/NWC/TT JV
20
20
E28/1959
Fraser Range - IGO JV
10
10
E28/2201
Fraser Range - IGO JV
10
10
E09/2427
Narryer Project
100
100
E09/2428
Narryer Project
100
100
E09/2429
Narryer Project
100
100
E09/2922
Narryer Project
100
100
E09/1985
Graphite Bull Project
100
100
LA09/102
Graphite Bull Project
100
100
LA09/103
Graphite Bull Project
100
100
E69/4182
Madman Project
100
100
EL80/5545
Lateron
100
100
EL80/5579
Centurion Project
100
100
MEP 008121028
MEP 008123390
MEP 008124215
SM-01
through
SM-54
CW-01
through
CW-215
Copper Wolf Project
(Section 16 T8NR1W G&SR Meridian)
Copper Wolf Project
(Section 9 T8NR1W G&SR Meridian)
Copper Wolf Project
(Section 29 T8NR1W G&SR Meridian)
Copper Wolf Project, Yavapai Co,
Arizona (Federal Lode Mining Claims)
100
100
100
100
100
100
100
100
Copper Wolf Project, Yavapai Co,
Arizona (Federal Lode Mining Claims)
100
100
Copper Wolf Project, Yavapai Co,
Arizona (Federal Lode Mining Claims)
0
100 (option)
CW-216
through
CW-342
ELA45/6228
Copper Wolf Project, Yavapai Co,
Arizona (Federal Lode Mining Claims)
0
100
Royale Project
100
100
ELA45/6229
Royale Project
100
100
ELA45/6230
Royale Project
100
100
ELA45/6231
Royale Project
100
100
ELA45/6232
Royale Project
100
100
Copper Chief
#1-5 &
Copper Chief
#18-19
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
ELA45/6233
Shogun Project
100
100
ELA45/6234
Shogun Project
100
100
Abbreviations and Definitions used in Tenement Schedule:
E = Exploration Licence (WA), ELA = Exploration Licence Application (WA), LA – Miscellaneous License Application (WA),
MEP = Mineral Exploration Permit (Arizona)
PO Box 661
Suite 1, First Floor
T. 08-9380 6063
Nedlands WA 6009
14-16 Rowland Street
E. info@buxtonresources.com.au
Subiaco WA 6008
www.buxtonresources.com.au
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Buxton Resources Limited
ABN
Quarter ended (“current quarter”)
86 125 049 550
31 March 2024
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date
(9 months)
$A’000
580
1,477
(494)
(3,005)
(b) development
-
-
(c) production
-
-
(d) staff costs
(276)
(838)
(e) administration and corporate costs
(132)
(555)
(a) exploration & evaluation
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
5
23
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other - GST
(53)
(2)
1.9
Net cash provided by/(used in) operating
activities
(370)
(2,900)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
(44)
(1)
(5)
(d) exploration & evaluation
-
-
(e) investments
-
-
(f)
-
-
(c) property, plant and equipment
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(9 months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements interests
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash provided by/(used in) investing
activities
(1)
(49)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
-
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
-
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other
-
-
3.10
Net cash from financing activities
-
-
4.
Net increase/(decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
1,583
4,145
4.2
Net cash provided by/(used in) operating
activities (item 1.9 above)
(370)
(2,900)
4.3
Net cash provided by/(used in) investing
activities (item 2.6 above)
(1)
(49)
4.4
Net cash from financing activities
(item 3.10 above)
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
4.5
Effect of movement in exchange rates on
cash held
444.
6
Cash and cash equivalents at end of
period
5.
Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
5.2
Current quarter
$A’000
Year to date
(9 months)
$A’000
5
21
1,217
1,217
Current quarter
$A’000
Previous quarter
$A’000
1,089
1,479
Call deposits
-
-
5.3
Term deposits
128
128
5.4
Credit card
-
(28)
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
1,217
1,583
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
43
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
Net cash from operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant net cash inflow (item 8.1 + item 8.2)
(370)
8.4
Cash and cash equivalents at quarter end (item 4.6)
1,217
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
-
$A’000
(370)
-
1,217
3.29
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
By the Board
Date:
...................................................................................
29 April 2024
Authorised by: ...................................................................................
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 5