Quarterly Activities Report
Released
Released
Announcement PDF
30th October 2015
ASX Release
Quarterly Activities Report for period ending 30th September 2015
Highlights
Double Magic Ni & Cu – West Kimberley
Phase One & Two RC and diamond core drilling has been completed
Assay results show RC drill hole DMRC0003 at Buxton’s 100 per cent-owned Double Magic
Ni-Cu project intersected 8m of massive to matrix sulphide grading 3.05% nickel and 1.87%
copper, within a broader intersection of 14m @ 2.04% nickel and 1.36% copper
A medium to high grade Ni-Cu sulphide body at Conductor D has been defined on three
sides but remains open to the north-west
The last step out hole drilled at Conductor D (diamond core hole DMDD0004) intersected 8
metres of visible Ni-Cu sulphides from 45m down hole, including 0.4m of massive sulphide
from 48.1m. This intersection is approximately 35 metres north-west of that in discovery
hole DMRC0003
Disseminated sulphides and minor massive sulphides were also intersected in the
diamond core hole DMDD0003 drilled at Conductor C
Heli-borne VTEMmax data acquisition completed
Zanthus Ni & Cu – Fraser Range
Buxton commenced a two hole, ~1,100m RC drilling program at its Zanthus Ni-Cu sulphide
project to test two high priority conductors for Ni-Cu sulphide mineralisation
Hole ZRC095 on conductor ZM02 was completed at 306m with a zone of disseminated
pyrrhotite & minor chalcopyrite in gneiss over 20m explaining the conductor. No
significant Ni-Cu mineralization was intersected
Hole ZRC096 targeting the large ZM07 conductor at ~700m depth temporarily suspended
at 256m due to difficulties associated with running sands in top 40m of the hole. ZRC096
to be continued at a later date once appropriate steel casing is manufactured
The drilling contractor has also undertaken to re-mobilise to Zanthus and re-enter or redrill ZRC096 at no cost to Buxton
Yalbra Graphite – Gascoyne Region
Metallurgical results show that commercial grades of flake graphite concentrate @ 91%
C(t) can be produced with 30% in the medium and coarse flake categories
After acid leaching, the combined concentrate was upgraded to 99.5% C(t)
Australia’s highest reported grade graphite resource: 4.0Mt @ 16.2% TGC (Inferred)
Substantial potential to expand resource along strike and down dip
Buxton is ready to commercialise the Yalbra Graphite Project by bringing in a strategic
partner for development and/or offtake
Corporate
Buxton successfully raised $2m for Double Magic & Fraser Range drilling by issuing
10,260,000 shares at 19.5c each
Cash balance (30 September 2015) of approximately $2.8 million
Hartleys Limited Issues Research Note
PO Box 9028
Subiaco WA 6008
Suite 1, First Floor
14-16 Rowland Street
Subiaco WA 6008
Tel: 08-9380 6063
Fax: 08-9381 4056
www.buxtonresources.com.au
info@buxtonresources.com.au
Double Magic Ni & Cu – West Kimberley
Figure 1. Location of the Double Magic Ni-Cu Project in the Kimberley region of Western Australia. Also
shown is the location of Panoramic’s Savannah Ni-Cu Mine.
On 10th August 2015, Buxton advised that it had discovered significant nickel and copper sulphide
mineralisation in its first reverse circulation (RC) drilling program at its 100% owned Double Magic NickelCopper (Ni-Cu) Project in Western Australia (Figure 1).
Assay results have been received for the strongly mineralised section of the discovery RC drill hole
DMRC0003 which intersected 8 metres at 3.05% nickel and 1.87% copper from 50 metres, within a
broader intersection of 14 metres at 2.04% nickel and 1.36% copper from 47 metres down hole (see
further details in Table 1 & 2 below).
DMRC0003 intersected 8 metres of massive and matrix sulphides from 50 metres, within a 15 metre
broader zone of disseminated sulphide. There were several additional disseminated sulphide zones and
one 1 metre massive sulphide zone from 41m. Note, all widths are down hole as true widths are not
currently known.
The massive and matrix sulphide intersections with visible pentlandite (nickel sulphide), chalcopyrite
(copper sulphide) from DMRC0003 are shown below in Figures 2 & 3. Mineralisation is hosted within
metamorphosed mafic (dolerite/gabbro) rocks of the Proterozoic Ruins Dolerite.
All drill holes completed during the program have been cased for downhole EM geophysics. This
downhole survey will assist with the detection of any additional off-hole EM conductors and better define
the orientation of known conductive bodies.
Figure 2. RC chips from the massive and matrix sulphide zone, from 50-58m in hole DMRC0003
Figure 3. Detailed photo examples of massive sulphide (left) and matrix style sulphides (right) taken from
50-58m downhole drill intercept in DMRC0003
Phase One Drill Program Results
Final assay data for all Phase One drilling has now been received, with significant (>0.25% Ni)
mineralisation intersected in a total of six drillholes. All such significant intercepts are listed in Table 1
overleaf, with details of all Buxton drillholes included as Table 2.
Recent mapping in the area of known conductors has indicated the mafic sequence/cycle may be locally
overturned, and that a chromium-rich unit in the dolerites may provide vectors to possible mineralisation
sites.
The presence of multiple younger, less deformed and highly magnetic dolerite dykes cross-cutting the
more typical Ruins Dolerite has also been recognised (Figure 4). One of these apparently barren dykes
is proximal to the mineralisation intersected in DMRC0003, and appears to have some displacement
across it, suggesting dyke emplacement may have exploited pre-existing structural features. Hole
DMRC0002 drilled directly down one such dyke.
Table 1 – Significant (>0.25% Ni) mineralisation intersected by Buxton. Intersections can include internal
results of up to 1m below 0.25% Ni.
Mapping and down-hole TEM results from DMRC0002 indicate that a conductive source may extend
down-dip from the intersection in DMRC0003, on the other side of the barren dyke. This potential downdip extension is the most obvious initial target for Phase Two drilling.
Drillholes, topography, mapped/interpreted surface geology, and modelled conductive plates have been
loaded into 3D-capable GIS software and evaluated. Ongoing interpretation and planning is being
conducted on-site in a full 3D environment.
Figure 4 – Simplified map of the central area of the Double Magic Project with modelled ground EM
conductors, interpreted geology, all completed drillholes at the completion of Phase 1 drilling, and selected
Buxton drilling results
Table 2 – Buxton’s Completed (Phase One) Drilling at Double Magic. Coordinates are MGA Zone 51
(GDA94)
SIGNIFICANT EVENTS AFTER THE BALANCE DATE
Subsequent to the balance date, Buxton announced that the Phase 2 RC drilling and diamond drilling
programs and most related field programs at the Double Magic Ni-Cu Project were complete, with only
down-hole HP TEM surveys ongoing.
This year’s exploration at the Double Magic Project has yielded a vast amount of new information
including encouraging drill results at Conductors D and C. The presence of high to very high grade NiCu sulphides in the area has been confirmed. On the strength of this, and as no exploration of any kind
has yet been completed outside the relatively small area of historic interest around Jack’s Hill, Buxton
also considers the untested potential of its regional tenements to be outstanding.
Receipt of laboratory assays will enable full assessment of drilling results, this coupled with evaluation of
both local DH TEM, HP FLTEM and the new regional VTEM dataset will drive planning of the next
program of works for the Double Magic Ni-Cu Project.
Zanthus Ni & Cu – Fraser Range
The Company’s 100% owned, highly prospective Zanthus Ni-Cu Project is located 60km along strike from
Sirius Resources’ Nova-Bollinger Ni-Cu discovery in the Fraser Range Nickel province, Western Australia.
The Company’s drilling program targeted two conductors, ZM02 and ZM07. Hole ZRC095 on conductor
ZM02 was completed at 306m with a zone of disseminated pyrrhotite and minor chalcopyrite in gneiss
over 20m explaining the conductor. No significant Ni-Cu mineralization was encountered.
Zanthus hole ZRC096 targeting the large ZM07 conductor at ~700m depth has been temporarily
suspended at 256m due to technical difficulties associated with running sands in the top 40m of the hole.
Additionally, the drilling contractor has undertaken to re-mobilise to Zanthus and re-enter (or re-drill to the
previously reached depth) ZRC096 at no cost to Buxton.
Yalbra Graphite – Gascoyne Region
Buxton reported initial flotation and acid purification test-work results for its high-grade Yalbra Graphite
Project in Western Australia.
Flotation batch test results from a representative fresh rock diamond drill sample grading 20.0% C(t)
returned a concentrate grade of 91% C(t). This concentrate showed a good proportion of medium to
coarse flake material with 30% falling into categories above +149 microns in size (Table 1). The overall
recovery of graphite was 80%, although this should be improved in future locked cycle tests. The process
involved a primary grind, a rougher flotation stage, 2 stages of polishing grind and 5 cleaner flotation
stages.
A final leaching stage using a combined H2SO4/HF solution to upgrade the concentrate was also
completed and showed that a final concentrate grading 99.5% C(t) could be achieved, with the coarser
size fractions grading as high as 99.7% C(t).
Yalbra is Australia’s highest reported grade graphite resource at 4.0Mt @ 16.2% TGC (Inferred) and has
considerable potential to be expanded along strike, and for discovery of additional resources. Additionally,
Buxton has shown commercial products can be produced from its very high grade Yalbra Graphite Project.
As such, the Company is now in a position to seek a development and/or offtake partner to assist in
commercialising the project.
Table 1. Flotation and purification results for the Yalbra Graphite Project.
Size
Size
Assays
Assays
Distribution
Microns (µm)
Tyler Mesh
Flotation
Conc.
C (t) %
Purified
Conc.
C (t) %
C (t) %
+297 µm
+48 mesh
91.8
99.7
6.6
+149 µm
+100 mesh
90.6
99.7
22.8
+74 µm
+200 mesh
90.0
99.5
31.2
-74 µm
-200 mesh
91.7
99.1
39.5
90.9
99.5
100.0
Weighted Avg.
Corporate
During the quarter, the Company issued 10,260,000 shares at 19.5c per share to raise approximately $2
million in a placement to sophisticated and professional investors.
Funds raised pursuant to the Placement will be used to fund:
An intensive technical program of results assessment, field mapping, on-ground geological
interpretation, structural analysis and several types of geological surveys (including down-hole
EM surveys and possibly high powered ground EM surveys) at the Double Magic Ni-Cu Project;
Phase 2 RC drilling and/or diamond drilling programmes at the Double Magic Ni-Cu Project; and
For working capital purposes
On 22nd September, Buxton announced that leading Australian broking and corporate advisory firm,
Hartleys Limited, has updated their research coverage on the Company.
A full copy of the research note is available for download on the Company’s website
http://buxtonresources.com.au/investor-centre/broker-research.html
Cash balance as at 30 September 2015 was approximately $2.9 million.
For further information please contact:
Eamon Hannon
Chief Executive Officer
ehannon@buxtonresources.com.au
Sam Wright
Company Secretary
sam@buxtonresources.com.au
Competent Persons
The information in this report that relates to exploration results and geology for the Yalbra and Zanthus projects is based on
information previously reported under the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves based on information compiled and/or reviewed by Dr Julian Stephens, Member of the Australian
Institute of Geoscientists and former Non-Executive Director for Buxton Resources Limited. No material changes have
occurred to this information. Dr Stephens has sufficient experience which is relevant to the activity being undertaken to qualify
as a “Competent Person”, as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves and consents to the inclusion in this report of the matters reviewed by him in the form and
context in which they appear.
The information in this report that relates to in-situ Mineral Resources is based on information compiled by David Williams of
CSA Global Pty Ltd and previously reported 25/2/2014. David Williams is a Member of the Australasian Institute of Mining
and Metallurgy, and a Member of the Australian Institute of Geoscientists and has sufficient experience, which is relevant to
the style of mineralisation and type of deposit under consideration, and to the activity he has undertaken, to qualify as a
Competent Person in terms of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’ (JORC Code 2012 Edition). David Williams previously consented to the inclusion of such information in the previous
report in the form and context in which it appeared. There have been no material changes to the information reported in the
previous report.
The information in this report that relates to exploration results and geology for the Double Magic Project is based on
information compiled by Mr Rolf Forster, Member of the Australasian Institute of Mining and Metallurgy, and Mr Derek
Marshall, Member of the Australian Institute of Geoscientists. Mr Forster is an Independent Consultant to Buxton Resources
Limited and Mr Marshall is a full-time employee. Mr Forster and Mr Marshall have sufficient experience which is relevant to
the activity being undertaken to qualify as a “Competent Person”, as defined in the 2012 edition of the Joint Ore Reserves
Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Forster
and Mr Marshall consent to the inclusion in this report of the matters based on the information in the form and context in
which it appears.
Appendix 1: Changes in interests in mining tenements - Buxton Resources Ltd
01/07/15 - 30/09/15
Tenement
Location
% at beginning of quarter
% at end of quarter
E 28/2201
Zanthus
100
100
E 28/1959
Zanthus
100
100
E 63/1595
Dempster
100
100
E 63/1582
Dempster
90
90
E 63/1720
Dempster
100
100
ELA 63/1675
Dempster
100
100
ELA 63/1676
Dempster
100
100
ELA 63/1677
Dempster
100
100
ELA 63/1685
Dempster
100
100
ELA 63/1686
Dempster
100
100
ELA 63/1687
Dempster
100
100
ELA 63/1688
Dempster
100
100
E 09/1985
Yalbra
85
85
E 09/1972
Yalbra
90
90
E 09/2101
Yalbra
100
100
ELA 66/87
Northampton
100
100
ELA 66/88
Northampton
100
100
E 66/90
Northhampton
100
100
E 66/91
Northhampton
100
100
E 66/92
Northhampton
100
100
ELA 77/2237
Yilgarn
100
100
ELA 77/2238
Yilgarn
100
100
E04/1533
Derby/West Kimberley
100
100
E04/2026
Derby/West Kimberley
100
100
E04/2060
Derby/West Kimberley
100
100
E04/2142
ELA 04/2406
Derby/West Kimberley
100
100
Derby/West Kimberley
100
100
ELA 04/2407
Derby/West Kimberley
100
100
ELA 04/2408
Derby/West Kimberley
100
100
ELA 04/2411
Derby/West Kimberley
100
100
ELA 70/4730
Northampton
100
100
Interests in mining
tenements relinquished,
reduced or lapsed
Interest in mining
tenements acquired or
increased
The mining tenements held
at the end of the quarter and
their location
Abbreviations and Definitions used in Tenement Schedule:
E
Exploration Licence
ELA
Exploration Licence Application